Seven Gabungan Rakyat Sabah (GRS) MPs will ask Parliament’s Public Accounts Committee (PAC) to investigate the 2019 termination of the project delivery partner (PDP) model for the Pan Borneo Highway, amid continuing political disputes over responsibility for delays.
Papar MP Armizan Mohd Ali said their memorandum, to be submitted next week, would seek to establish whether the decision and subsequent transition to conventional contracting had disrupted construction, delayed contractor appointments and increased costs.
“The scope of the investigation should be expanded to cover the basis and implications of the termination of the PDP model,” he said after officiating at the closing ceremony of the IP SPARK 2026 programme on Sunday.
The PDP arrangement was terminated on Sept 22, 2019, following a recommendation by the Sabah government led by Warisan’s Shafie Apdal. The federal government subsequently shifted to conventional procurement, with existing contractors reappointed and new packages tendered.
Armizan said uncertainty following the change of government in May 2018 had stalled construction work for more than a year.
He also pointed to official Works Ministry responses in Parliament in 2022 and October this year identifying the PDP termination as one of the causes of delays.
“So this is not political talk or political issues determined by people, but an official response in the Dewan Rakyat,” he said.
The issue has become a political blame game between GRS and Warisan. GRS leaders have questioned the previous administration’s recommendation to end the PDP model, while Warisan has argued that the final decision rested with the federal government.
The transition also coincided with rising construction material prices and the Covid-19 pandemic, adding pressure on project costs and schedules.
Phase 1A comprises 15 work packages. Under the conventional system, 11 existing contractors were reappointed, one package was retendered and three new packages were tendered. Some appointments were only completed in 2021.
Armizan said contractors should also be called to explain the difficulties they faced during the transition.
“We hope that not only government agencies but also the contractors will be called to these proceedings to hear about the pressures and issues they faced,” he said.
The PAC agreed on Oct 19 to investigate the project’s management, financial governance and physical progress following the Auditor General’s Report Series 2/2026.
Armizan said the memorandum was not intended to find fault with any party, but to ensure political considerations did not undermine the implementation of major public infrastructure projects.